TRANSFORMER COMMISSIONING
Insulation
Resistance
All
know that the resistance of a pure insulation is infinity. But to no extend we
can make a pure insulation. So we have a small leakage current to flow through
insulation depending upon the voltage applied. Thus as the result we get a
resistance value in the range of Mega Ohms(MΩ) or Giga Ohms(GΩ). Here the applied voltage is DC. We have
separate kit for injecting the DC voltage. Usually that equipment is known as
megger.
The
two windings are connected as in the diagram above and Megger is used to measure
the insulation resistance. It applies a high voltage normally 500V or 1kV for
time period of minimum 30 seconds to One minute and the respective resistance
are noted down. Usually for a new transformer, result value will be in Giga
Ohms(GΩ). During the ageing, deposition of dust, moisture and other unwanted
particles can cause the megger value to reduce. So to gain the resistance back
to normal, the dust deposited should be removed, moisture should be reduced
using heaters and other necessary steps must be taken in account.
Tan-delta
Test
Also
known as Loss Angle Test or Dissipation Factor Testing do the same process what
Insulation Resistance do. The difference here is instead of DC we inject AC
voltage. It’s principle of working is that all insulators are pure capacitive
in nature because one end is energised while the other is connected to ground.
So for a pure capacitor the current will lead 90 degree to voltage. Since there
is no pure capacitor we will get some difference in the mentioned angle. This
difference is known as loss angle. With this test we measure the loss in angle
measure due to ageing of transformer oil, windings and bushing, etc.
All
insulators will have a capacitive and resistive nature. So they consume both
capacitive current and resistive current. Initial in the commissioning stage
the angle delta(δ) will be as low as possible. Due to ageing there will develop
a resistive current which increases the angle measurement and beyond a
particular value the equipment cannot be put in service. There is no such
method to increase the tan-delta value during maintenance.
Ratio
Test
As
the name implies the ratio test is done to note whether the transformation
ratio of a transformer is as specified in the name plate. This test is carried
out in all the taps of transformer. Supply is three phase and is measurement is
recorded in phase to phase values and phase to neutral values. Now connection
is established as in the figure shown below.
Now
all the three phases will be charged instantaneously and the secondary voltage
(phase-phase and phase-neutral) in all respect will be recorded. Fist it is
done on the lower tap and carried out in the continual taps. Recorded values
will be finally compared with the theoretical values then obtained.
Core
Balance Test
Test
conducted both on high voltage and low voltage winding. At first we inject
voltage to terminals R and N. After that voltage is measured from terminal Y-N
and B-N. The same process id done in all three cores and the other core values
are recorded. The same is repeated on the second winding too.
Above
diagram shows the arrangement of windings in a transformer core. Consider this
windings are star connected at primary and secondary. Now if we energise the R
phase terminal and the star point, we observe an induced emf in the other two
terminals of the same windings. And measurement will be in the ratio, Y=75% and
B= 25% of the injected value of voltage. Summation of Y phase and B phase will
be equal to R phase. Then voltage is applied on Y and star point. Now voltage
developed in R phase and B phase are same and is 50% each. So Y phase is the
sum of both R and B phase. The same procedure is repeated on B phase. Now
obtained measurement in R phase is 25% and Y phase is 75%. The same process is
repeated in secondary winding also and measurement is noted down.
Magnetisation
Test
It’s simple
test to find out how much current the transformer consumes for initializing the
magnetic flux over the core. Three phase supply is given to the HV winding and
the LV is marked open. Now the current consumed is measured and recorded. It is
said that magnetisation current should be limited to One(1%) percentage of the
FLA( full load amperes).
Vector
Grouping Test
It’s
a way of labelling the HV and LV winding of a three phase transformer. Take an
example YNd11, the first two letter
indicates the primary winding usually in capital letters and the second
alphabet denotes the secondary winding and the number denoting the phase shift
between HV and LV winding. Here (YNd11)
we can say that primary is a star connection with neutral and secondary is a delta
connected with a phase shit of 30degrees lagging with primary. The figure above
is an example of testing vector grouping in a Y-Y(YNyn0) transformer. A
temporary shorting is given to the primary neutral (N) and secondary U-phase.
Three phase voltage is applied on the primary side and the voltages are measure
likewise in the figure.
Short-Circuit
Test
This
test is mainly done to find whether there is any manufacturing defects in the
OLTC windings and connections. As shown in the diagram, the Low Voltage (LV)
side of the transformer is short circuited and a small three phase voltage is
applied on the High Voltage (HV) side through a moving iron ammeter. The
ammeter is to be selected to measure the maximum rated current in the primary. BCT or the Bushing Current Transformer
which supplies the input for the winding temperature measurement is also
checked at the normal tap of the transformer and confirms the BCT ratio is as
specified by manufacturer. Three phase supply is switched on and from lower tap
to higher the current is measured and noted. In the meantime of tap changing
the three ammeter currents are visually checked to ensure that there is no
fluctuation in any of the meter during the change over. This ensures that a
secure connection in the diverter switch of OLTC mechanism.
REF
Stability Test
A
method of protecting both winding of a transformer for earth-fault. It’s
basically a unit protection. REF should only act for in ZONE faults. Testing
procedure includes injecting primary current through R-phase CT and NCT in
series so there will be no spill in relay. Note that both CT should have the P2 side towards transformer. If there
is any spill then the secondary connection of any one of the CT’s is inversed.
(This can be discussed in later posts)
Differential
Stability Check
Foremost
protection in transformer is differential protection. It protects almost 60% to
70% of the total winding for particularly phase to phase faults. Rest of the
windings is protected by REF relays. A differential relay operates on two quantities,
one is the operating or differential current and the second is restraining or
bias current. So during commissioning it’s important to check all the
connections such as jumpers, CT connections in Primary and it’s secondary leads
are in proper terminations. The inputs of differential relay is from both HV
and LV CT’s. So testing procedure
includes, applying # phase supply on the primary end including CTs while the
secondary side will be shorted and earthed after the LV CTs. So differential
current inside the relay will be zero and biasing current will be high. For the
next step of testing the input supply will be given to transformer by bypassing
any one CT at one END. So that CT will not read the SC current while the other
CT’s read their respective primary values. This unbalance creates a
differential current to rise and initiates a trip signal when the operating
current moves up beyond the restraining value.
Circuit
Breaker Tripping test on Faults
So finally, the
protective relays will be tested via a secondary injection test setup and
confirms no false tripping occur while it trips for every faults. Now all
transformer trouble alarms and trips will be checked from yard. Trouble alarms
include Buccholz Trip/Alarm, Pressure Relief Valve, Winding Temperature
Trip/Alarm, Oil Temperature Trip/Alarm, Oil Surge Relay, Magnetic Oil Gauge,
etc.
Comments
Post a Comment